Badshapur-Sohna road work delayed again

Neighbourhood News Desk/Gurugram/Garima Kotroo

Related image

The Project to extend Badshapur-Sohna road has been delayed by another month due to inadequate land acquisition.  The 23 km signal-free road has only 70% of land for upgradation whereas to commence any project, National Highways Authority of India (NHAI) requires 80% land.

The NHAI officials said “payment of Rs 64 crore has been made to ‘Competent Authoritiy, Land Acquisition’ (CALA) but the possession is yet to be given”. However, the upgradation work has been divided into two phases.

One comment

Leave a Reply

Please log in using one of these methods to post your comment:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Google+ photo

You are commenting using your Google+ account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s